Address area: commercial building near Riverton City Park, Riverton, UT 84065 (specific address confidential per business owner request). Project completion: August 2025. Scope: Commercial packaged rooftop unit (RTU) replacement for approximately 4,200 sq ft restaurant operation, replacing 2003 original construction 7.5-ton RTU with modern high-efficiency Carrier packaged gas/electric unit. This case study documents the pre-installation commercial evaluation, business continuity coordination minimizing restaurant closure time, crane lift coordination for rooftop equipment replacement, commissioning verification for commercial building conditioning, and business owner outcome including operating cost impact analysis.
Commercial building housing restaurant operation: approximately 4,200 sq ft occupied space with dining area (2,400 sq ft), kitchen (1,200 sq ft including cooking line and prep area), and support areas (walk-in cooler, freezer, office, restrooms), single-story flat-roof commercial construction typical of 2003 commercial development, and building located in commercial corridor near Riverton City Park with regular customer traffic patterns.
2003 original construction packaged rooftop unit:
Pre-replacement evaluation confirmed replacement rather than repair: (1) 22 year-old equipment beyond typical service life with cascading component failure pattern; (2) R-22 refrigerant phase-out increases cost of continued service scenarios; (3) 80% AFUE heating and standard cooling efficiency substantially less efficient than modern packaged unit options; (4) recent refrigerant leak indicates aged refrigerant piping and coil condition, likely to produce ongoing repair scenarios; and (5) restaurant operation depends critically on HVAC reliability, and continued patching of aged equipment risks business-disrupting failure during peak dining periods.
Restaurant operation impact considerations: restaurant open 6 days per week (Tuesday–Sunday), lunch service 11am–2pm and dinner service 5pm–9pm daily, weekend brunch service Saturday–Sunday 10am–2pm, and Monday closure day for maintenance and prep. Business owner priority: minimize customer-facing closure time, ideally maintain normal operations with rooftop replacement completed during single Monday closure or overnight window.
Replacement timeline planned as follows: (1) Sunday evening after dinner service close (9pm), equipment staging and pre-work preparation; (2) Monday full-day installation (7am–7pm) with crane lift scheduled 8am–10am window for existing unit removal and new unit setting; (3) Monday evening commissioning verification and cleanup; (4) Tuesday morning normal operations resume with new HVAC system in service.
August installation timing produced ambient conditions concern for restaurant kitchen operation: kitchen equipment (grill line, fryer, ovens) produces substantial heat load requiring active cooling for cook safety and food safety, cooler than main dining area during summer months, and full day without operational RTU during high summer conditions could produce interior temperatures exceeding safe kitchen operation range. Temporary cooling deployment: two 60,000 BTU portable spot coolers deployed in kitchen prep area during installation day, providing critical cooling for prep work being conducted for Tuesday reopening, and portable spot coolers routed to exterior venting for exhaust heat.
Carrier Weathermaker 48TC packaged gas/electric rooftop unit selected:
Commercial load calculation for the restaurant:
Sunday evening preparation (9pm–11pm): existing rooftop curb inspected and verified compatible with new equipment (Carrier 48TC uses standard commercial curb footprint), electrical service verified adequate (existing 60 amp 208V 3-phase service adequate for new equipment), gas service verified adequate (existing 1" gas line with 2 psi service pressure adequate), and staging area set up in parking lot for crane lift operation Monday morning.
Monday installation day timeline:
Rooftop curb compatibility was successful due to Carrier 48TC using standard commercial curb footprint matching Trane Voyager curb dimensions. Some replacement scenarios require curb adapter installation adding 4–6 hours to installation timeline; this project avoided that scope through equipment selection compatible with existing curb.
Combustion analyzer verification at both low-fire and high-fire operation:
Cooling system verification at 82°F outdoor ambient during afternoon commissioning:
Integrated economizer verification: outdoor air damper actuation verified through full range, mixed air temperature sensor calibration verified, economizer control setpoint programmed for 65°F outdoor changeover, economizer will provide free cooling during appropriate outdoor conditions reducing compressor operation and improving overall efficiency.
Business continuity achieved as planned: restaurant reopened for normal Tuesday operations with new HVAC system fully commissioned, no lost revenue beyond regular Monday closure, and customer-facing operation not affected by replacement scope.
Operating cost improvement expected across full annual cycle:
Business owner enrolled in Commercial Maintenance Contract at $980/year: quarterly service visits (versus twice-yearly Comfort Club for residential), pre-season heating and cooling verification, filter service (commercial filters replaced more frequently given restaurant kitchen contamination), belt inspection and adjustment, economizer operation verification, drain pan and drain line service, and priority emergency response for restaurant business continuity considerations.
Commercial packaged rooftop unit (RTU) replacement and service, business continuity coordination minimizing customer-facing service disruption during replacement, crane lift coordination with supplier and lift service for rooftop equipment placement, temporary spot cooler deployment for kitchen safety during summer installations, Carrier Weathermaker commercial packaged gas/electric RTU installation with two-stage compressor and VFD blower operation, integrated economizer for free cooling during appropriate outdoor conditions, R-22 refrigerant recovery per EPA Section 608 requirements from replaced equipment, commercial ASHRAE 62.1 ventilation requirements coordination, Rocky Mountain Power Wattsmart commercial cooling rebate coordination, quarterly Commercial Maintenance Contract with priority emergency response, and 24/7 emergency response all route through our office at 14659 S 855 W in Bluffdale serving the greater Salt Lake Valley commercial buildings including Riverton City Park area.